What are the HDB renovation hours?
HDB allows general renovation works from 9am to 6pm, Monday to Saturday. Noisy works such as hacking, tile cutting and heavy drilling are allowed only from 9am to 5pm on weekdays. No renovation is allowed on Sundays and public holidays, and noisy works are also not allowed on the eve of major public holidays.
Planning your renovation schedule?
WhatsApp us your key collection date and we will map out a timeline that fits HDB’s hours.
WhatsApp us your floor plan See our HDB interior design service
HDB Renovation Timing at a Glance
| Type of work | Monday to Friday | Saturday | Sunday and public holidays |
|---|---|---|---|
| General works, such as painting, plastering and floor screed | 9am to 6pm | 9am to 6pm | Not allowed |
| Noisy works, such as hacking, removing tiles, tile cutting and heavy drilling | 9am to 5pm | Not allowed | Not allowed |
Noisy works are also not allowed on the eve of major public holidays: New Year’s Day, Lunar New Year, Hari Raya Puasa, Deepavali and Christmas. Source: HDB renovation guidelines.
Other HDB Timing Rules to Know
Hacking must finish within 3 days
Demolition and the removal of wall and floor finishes must be completed within three consecutive days. Plan all the hacking together at the start of the job. See what you can and cannot remove in our guide to HDB hacking rules.
Tell your neighbours 5 days before
Give written notice to the neighbours within two units of your flat at least five days before works begin, and display a notice outside your flat with the contractor’s details and the renovation dates.
Finish within the permit period
Renovation must be completed within three months for a newly completed block and within one month for an existing block, counted from the date of the permit.
Get the permit first
Works such as hacking walls, changing floor finishes and altering bathrooms need an HDB permit before they start. Your contractor applies for it, and the contractor must be listed in HDB’s Directory of Renovation Contractors. See how long HDB takes to approve a renovation.

How to Plan Your Renovation Around the Hours
The rules shape the order of work more than most owners expect. This is how our project managers schedule a typical job.
- Hacking first, on weekdays. It has to fit into three consecutive weekdays, so it is booked as one block, not spread across weeks.
- Tiling and drilling on weekdays. Tile cutting and drilling for carpentry are noisy works, so they stop at 5pm and do not run on Saturdays.
- Quiet works on Saturdays. Painting, plastering, touch-ups and cleaning can continue until 6pm on Saturdays, which keeps the job moving.
- Watch the calendar. A public holiday and its eve can take two working days out of a week. Check the dates before fixing your move-in day.
- Leave a buffer. Deliveries and inspections slip. Leave spare days before the permit period ends.
For the full sequence from key collection to move-in, see our HDB renovation checklist. For drilling rules in detail, see HDB drilling time.

What Happens if the Rules Are Broken?
Neighbours can report noise outside the allowed hours to HDB, and the contractor can be penalised. Complaints also slow the job down, because works may have to stop while they are looked into. A contractor who knows the rules will plan around them from the start, so this should never become your problem.
HDB Renovation Timing: Common Questions
Can renovation be done on Saturday in an HDB flat?
General works can, from 9am to 6pm. Noisy works such as hacking, tile cutting and heavy drilling cannot.
Can I renovate on Sunday or a public holiday?
No. Renovation works are not allowed on Sundays and public holidays.
How long do I have to finish my HDB renovation?
Three months for a newly completed block and one month for an existing block, from the date of the permit.
Do I need to inform my neighbours?
Yes. Give written notice to the neighbours within two units at least five days before works start.